Tahoe City Public Utility District Awards Construction Contract to Vinciguerra Construction Inc (November 2026)
- Disclosed value
- $419,908.08 payment due this estimate; $5,420,000.33 cumulative net earnings; revised contract amount $5,922,445.00; maximum authorized contract amount $6,514,890.00
- From report
- Approved
- Nov 20, 2026
The 30-second brief
Tahoe City Public Utility District approved a $419,908.08 progress payment to Vinciguerra Construction, Inc. for Phase 4 of the Madden Creek Water System Improvement Project. Cumulative net earnings reached $5,420,000.33 under the revised $5,922,445.00 construction contract, with work 96% complete.
Vinciguerra Construction Inc holds this construction contract with Tahoe City Public Utility District. Its other public contracts on record include work for South Tahoe Public Utilities District and South Tahoe Public Utility District.
Term as filed: 203 days revised contract time; 173 days elapsed.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $419,908.08 payment due this estimate; $5,420,000.33 cumulative net earnings; revised contract amount $5,922,445.00; maximum authorized contract amount $6,514,890.00
- Document date
- November 20, 2026
- Term
- 203 days revised contract time; 173 days elapsed
- Source document
- Tahoe City Public Utility District Report Madden Creek Water System Improvement Project Phase 4 Progress Pay Estimate No. 6 2026-11-20 (Report)
Vinciguerra Construction Inc's other public contracts
More Tahoe City Public Utility District contracts
Questions about this contract
Who was awarded the construction contract by Tahoe City Public Utility District?
Vinciguerra Construction Inc was awarded this construction contract by Tahoe City Public Utility District, as recorded on November 20, 2026. The contract value is $419,908.08 payment due this estimate; $5,420,000.33 cumulative net earnings; revised contract amount $5,922,445.00; maximum authorized contract amount $6,514,890.00.
How much is the Vinciguerra Construction Inc contract with Tahoe City Public Utility District worth?
The Vinciguerra Construction Inc contract with Tahoe City Public Utility District is valued at $419,908.08 payment due this estimate; $5,420,000.33 cumulative net earnings; revised contract amount $5,922,445.00; maximum authorized contract amount $6,514,890.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Tahoe City Public Utility District Report Madden Creek Water System Improvement Project Phase 4 Progress Pay Estimate No. 6 2026-11-20 (Report), dated November 20, 2026 from Tahoe City Public Utility District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Vinciguerra Construction Inc hold?
Vinciguerra Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Tahoe City Public Utility District currently buying?
Explore Tahoe City Public Utility District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.