CONSTRUCTIONAMENDED

SFPUC Adds Dam Repair Contingency for Njirich

The SFPUC approved a $1.65 million contingency increase and 183 additional calendar days for Njirich & Son, Inc.'s Cherry Valley Dam and Eleanor Dam repair contract. The revised cost limit is $11,191,730 and the revised duration limit is 683 days.

Document date · September 21, 2026

Track San Francisco Public Utilities Commission contracts

Get alerts when new contracts are awarded or existing ones approach renewal at San Francisco Public Utilities Commission.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Increase of $1,650,000 to cost contingency; revised cost limit $11,191,730
Contract type
CONSTRUCTION
Contract term
Increase of 183 calendar days to duration contingency; revised duration limit 683 consecutive calendar days
Renewal
Amended through increased cost and duration contingencies; revised limits are $11,191,730 and 683 calendar days.
Document type
Agenda
Source document
San Francisco Public Utilities Commission Agenda 2026-09-22

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by San Francisco Public Utilities Commission?

Njirich & Son Inc was awarded this construction contract by San Francisco Public Utilities Commission, as recorded on September 21, 2026. The contract value is Increase of $1,650,000 to cost contingency; revised cost limit $11,191,730.

How much is the Njirich & Son Inc contract with San Francisco Public Utilities Commission worth?

The Njirich & Son Inc contract with San Francisco Public Utilities Commission is valued at Increase of $1,650,000 to cost contingency; revised cost limit $11,191,730, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in San Francisco Public Utilities Commission Agenda 2026-09-22 (Agenda), dated September 21, 2026 from San Francisco Public Utilities Commission. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Njirich & Son Inc hold?

Njirich & Son Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Njirich & Son Inc's profile

What is San Francisco Public Utilities Commission currently buying?

Explore San Francisco Public Utilities Commission's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View San Francisco Public Utilities Commission's profile