CONSTRUCTIONAMENDED

Victory Building Team Change Order Adds $12,544.40

Nueces County approved Change Order No. 005 for Victory Building Team on its medical examiners office construction project. The $12,544.40 amendment adds window and sidewalk work and extends the contract by 72 days, bringing the new contract sum to $7,742,133.50.

Document date · August 7, 2026

Track Nueces County contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Nueces County.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
The contract sum will be increased by this Change Order in the amount of $12,544.40; new Contract Sum including this Change Order will be $7,742,133.50
Contract type
CONSTRUCTION
Contract term
Contract date 05-06-2024; Change Order 005 dated 08-07-2026; contract time increased by 72 days; new date of Substantial Completion 08-31-2026
Renewal date
2026-08-31
Renewal
Amendment/change order to existing general construction contract; adds 72 days to the contract time and sets new substantial completion date to 2026-08-31. Prior authorized change orders totaled $730,189.10.
Document type
Contract
Source document
Nueces County Contract Change Order General Construction 2026-08-07

Related contracts

Other contracts from Victory Building Team.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Nueces County?

Victory Building Team was awarded this construction contract by Nueces County, as recorded on August 7, 2026. The contract value is The contract sum will be increased by this Change Order in the amount of $12,544.40; new Contract Sum including this Change Order will be $7,742,133.50.

How much is the Victory Building Team contract with Nueces County worth?

The Victory Building Team contract with Nueces County is valued at The contract sum will be increased by this Change Order in the amount of $12,544.40; new Contract Sum including this Change Order will be $7,742,133.50, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Nueces County Contract Change Order General Construction 2026-08-07 (Contract), dated August 7, 2026 from Nueces County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Victory Building Team hold?

Victory Building Team may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Victory Building Team's profile

What is Nueces County currently buying?

Explore Nueces County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Nueces County's profile