Mount Zion village Awards Construction Contract to Corrective Asphalt Materials (June 2026)

The Mt. Zion Village Board awarded the 2026 Asphalt Treatment Various Roadways Project to Corrective Asphalt Materials based on a sole bid of $51,963.00. A planned change order removing pavement core testing will reduce the contract by $9,825.52 for a final amount of $42,137.48, with work to be completed by August 31, 2026.

Document date · June 15, 2026

Track Mount Zion village contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Mount Zion village.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$51,963.00, reduced by change order of $9,825.52 to a final contract amount of $42,137.48
Contract type
CONSTRUCTION
Contract term
Project to be completed no later than August 31, 2026
Renewal date
2026-08-31
Renewal
Single-year construction project with a required completion date of August 31, 2026; a change order will remove pavement core testing and reduce the contract amount to align with the engineer’s estimate.
Document type
Minutes
Source document
Mt. Zion Village Board of Trustees Meeting Minutes 2026-06-15

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Mount Zion village?

Corrective Asphalt Materials was awarded this construction contract by Mount Zion village, as recorded on June 15, 2026. The contract value is $51,963.00, reduced by change order of $9,825.52 to a final contract amount of $42,137.48.

How much is the Corrective Asphalt Materials contract with Mount Zion village worth?

The Corrective Asphalt Materials contract with Mount Zion village is valued at $51,963.00, reduced by change order of $9,825.52 to a final contract amount of $42,137.48, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Mt. Zion Village Board of Trustees Meeting Minutes 2026-06-15 (Minutes), dated June 15, 2026 from Mount Zion village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Corrective Asphalt Materials hold?

Corrective Asphalt Materials may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Corrective Asphalt Materials's profile

What is Mount Zion village currently buying?

Explore Mount Zion village's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Mount Zion village's profile