CONSTRUCTIONRECOMMENDED

MISD Recommends CORE Construction Change Order Approval

Mansfield Independent School District recommends approving Change Order #1 with CORE Construction for the 2024 Bond Package ELA2 Early Learners Academy. The change adds 56 days to the construction schedule for permitting delays and inclement weather without increasing the $50,239,684 contract value.

Document date · September 21, 2026

Track Mansfield Independent School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Mansfield Independent School District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$0.00 change order; original and current contract amount $50,239,684.00
Contract type
CONSTRUCTION
Contract term
Adds 56 days to the construction completion date
Renewal
Change Order #1 extends the construction completion schedule by 56 days; no contract-price increase. The change order incorporates RFPs developed from April 2025 through September 2026.
Document type
StaffReport
Source document
Mansfield Independent School District StaffReport Change Order #1 ELA2 Early Learners Academy 2026-09-22

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Mansfield Independent School District?

Core Construction was awarded this construction contract by Mansfield Independent School District, as recorded on September 21, 2026. The contract value is $0.00 change order; original and current contract amount $50,239,684.00.

How much is the Core Construction contract with Mansfield Independent School District worth?

The Core Construction contract with Mansfield Independent School District is valued at $0.00 change order; original and current contract amount $50,239,684.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Mansfield Independent School District StaffReport Change Order #1 ELA2 Early Learners Academy 2026-09-22 (StaffReport), dated September 21, 2026 from Mansfield Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Core Construction hold?

Core Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Core Construction's profile

What is Mansfield Independent School District currently buying?

Explore Mansfield Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Mansfield Independent School District's profile