Horsepen Run Sewer Vault Design Task Order Recommended
- Disclosed value
- $334,500, with an approximate five percent (5%) contingency and total authorized budget of $351,200
- From staffreport
- Document date
- Nov 12, 2026
The 30-second brief
Loudoun Water staff recommends awarding Michael Baker International Inc. a design task order for the Horsepen Run Sewer Vault Meter project. The task order is valued at $334,500, with a contingency bringing the total authorized budget to $351,200, under an existing BOA contract.
Michael Baker International Inc holds this professional services contract with Loudoun Water. Its other public contracts on record include work for Bay County and Hillsborough County Aviation Authority.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Professional Services
- Amount
- $334,500, with an approximate five percent (5%) contingency and total authorized budget of $351,200
- Document date
- November 12, 2026
- Agency
- Loudoun Water
- Source document
- Loudoun Water StaffReport Approval of Design Task Order Horsepen Run Sewer Vault Meter 2026-11-12 (StaffReport)
Michael Baker International Inc's other public contracts
More Loudoun Water contracts
Questions about this contract
Who was awarded the professional services contract by Loudoun Water?
Michael Baker International Inc was awarded this professional services contract by Loudoun Water, as recorded on November 12, 2026. The contract value is $334,500, with an approximate five percent (5%) contingency and total authorized budget of $351,200.
How much is the Michael Baker International Inc contract with Loudoun Water worth?
The Michael Baker International Inc contract with Loudoun Water is valued at $334,500, with an approximate five percent (5%) contingency and total authorized budget of $351,200, covering professional services work.
What type of contract is this?
This is a Professional Services contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Loudoun Water StaffReport Approval of Design Task Order Horsepen Run Sewer Vault Meter 2026-11-12 (StaffReport), dated November 12, 2026 from Loudoun Water. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Michael Baker International Inc hold?
Michael Baker International Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Loudoun Water currently buying?
Explore Loudoun Water's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.