CONTRACTAMENDED

STEAM Construction Contract Amended for Flint Design-Build

Las Positas College logoLas Positas College
Disclosed value
$85,939,328.00 lump sum, not-to-exceed; new contract amount $114,082,212.00
From contract
Document date
Feb 27, 2026

The 30-second brief

What it covers

Chabot-Las Positas Community College District amended its lease-leaseback construction agreement with Flint Design-Build LLC for the STEAM Project at Las Positas College. Modification No. 7 adds $85,939,328.00 and establishes a revised total contract amount of $114,082,212.00.

Who holds it

Flint Design-build LLC holds this construction contract with Las Positas College. Its other public contracts on record include work for Monterey Peninsula College.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$85,939,328.00 lump sum, not-to-exceed; new contract amount $114,082,212.00
Document date
February 27, 2026
Source document
Chabot-Las Positas Community College District Contract Modification No. 7 for STEAM Project 2026-02-27 (Contract)

Flint Design-build LLC's other public contracts

More Las Positas College contracts

Questions about this contract

Who was awarded the construction contract by Las Positas College?

Flint Design-build LLC was awarded this construction contract by Las Positas College, as recorded on February 27, 2026. The contract value is $85,939,328.00 lump sum, not-to-exceed; new contract amount $114,082,212.00.

How much is the Flint Design-build LLC contract with Las Positas College worth?

The Flint Design-build LLC contract with Las Positas College is valued at $85,939,328.00 lump sum, not-to-exceed; new contract amount $114,082,212.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Chabot-Las Positas Community College District Contract Modification No. 7 for STEAM Project 2026-02-27 (Contract), dated February 27, 2026 from Las Positas College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Flint Design-build LLC hold?

Flint Design-build LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Las Positas College currently buying?

Explore Las Positas College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo