CONSTRUCTIONAPPROVED

Las Gallinas Valley Sanitary Dist Awards Construction Contract to Bauman Landscape & Construction Inc (October 2026)

The District accepted Bauman Landscape and Construction’s completed Phase 2 foundation project for the Multipurpose Laboratory Building. The final project cost was $774,906.25, including $77,666.25 in additive change orders.

Document date · October 1, 2026

Track Las Gallinas Valley Sanitary Dist contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Las Gallinas Valley Sanitary Dist.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Original contract: $697,240; additive change orders: $77,666.25; final project cost: $774,906.25
Contract type
CONSTRUCTION
Contract term
Contract entered November 17, 2025; work completed June 29, 2026; completion accepted October 1, 2026
Renewal date
2026-10-01
Document type
AgendaPacket
Source document
Las Gallinas Valley Sanitary District AgendaPacket Board Meeting 2026-10-01

Related contracts

Other contracts from Bauman Landscape & Construction Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Las Gallinas Valley Sanitary Dist?

Bauman Landscape & Construction Inc was awarded this construction contract by Las Gallinas Valley Sanitary Dist, as recorded on October 1, 2026. The contract value is Original contract: $697,240; additive change orders: $77,666.25; final project cost: $774,906.25.

How much is the Bauman Landscape & Construction Inc contract with Las Gallinas Valley Sanitary Dist worth?

The Bauman Landscape & Construction Inc contract with Las Gallinas Valley Sanitary Dist is valued at Original contract: $697,240; additive change orders: $77,666.25; final project cost: $774,906.25, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Las Gallinas Valley Sanitary District AgendaPacket Board Meeting 2026-10-01 (AgendaPacket), dated October 1, 2026 from Las Gallinas Valley Sanitary Dist. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Bauman Landscape & Construction Inc hold?

Bauman Landscape & Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Bauman Landscape & Construction Inc's profile

What is Las Gallinas Valley Sanitary Dist currently buying?

Explore Las Gallinas Valley Sanitary Dist's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Las Gallinas Valley Sanitary Dist's profile