CONSTRUCTIONAMENDED

Time Extension Change Order for Bells Sewer Project

Greater Texoma Utility Authority will consider approving Change Order No. 1 with Hayes Construction, LLC for the City of Bells’ Branch Street Sewer Project, extending the substantial completion date to August 29, 2026 and increasing contract time to 75 days without changing the contract amount. The amendment addresses scheduling delays impacting construction sequencing.

Document date · August 17, 2026

Track Greater Texoma Utility Authority contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Greater Texoma Utility Authority.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Contract time extended from 45 days to 75 days; Substantial Completion date revised from July 30, 2026 to August 29, 2026
Renewal date
2026-08-29
Renewal
Change Order No. 1 extends the contract time by 30 days and revises substantial completion to August 29, 2026; no cost change and future changes would be via additional change orders.
Document type
AgendaPacket
Source document
Greater Texoma Utility Authority Board Meeting Agenda Packet 2026-08-17

Related contracts

Other contracts from Hayes Construction Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Greater Texoma Utility Authority?

Hayes Construction Llc was awarded this construction contract by Greater Texoma Utility Authority, as recorded on August 17, 2026.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Greater Texoma Utility Authority Board Meeting Agenda Packet 2026-08-17 (AgendaPacket), dated August 17, 2026 from Greater Texoma Utility Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Hayes Construction Llc hold?

Hayes Construction Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Hayes Construction Llc's profile

What is Greater Texoma Utility Authority currently buying?

Explore Greater Texoma Utility Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Greater Texoma Utility Authority's profile