CONSTRUCTIONONGOING

Coastal Wetlands Park Construction Progresses with ADA Delay

Grand Isle Shipyard continues work on Coastal Wetlands Park improvements for the Greater Lafourche Port Commission, pouring the deck structure and targeting completion of walkways and landscaping by the end of June 2026. Occupancy of the second floor will be delayed pending delivery of the ADA lift.

Document date · June 10, 2026

Track Greater Lafourche Port Commission (includes airport) contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Greater Lafourche Port Commission (includes airport).

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Through completion of Coastal Wetlands Park improvements; landscaping by end of June 2026, ADA lift delayed
Renewal
Work continues with partial completion milestones; occupancy delayed due to ADA lift fabrication delay, suggesting schedule extension though no formal amendment noted.
Document type
Minutes
Source document
Greater Lafourche Port Commission Board Meeting Minutes 2026-06-10

Related contracts

Other contracts from Grand Isle Shipyard.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Greater Lafourche Port Commission (includes airport)?

Grand Isle Shipyard was awarded this construction contract by Greater Lafourche Port Commission (includes airport), as recorded on June 10, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Greater Lafourche Port Commission Board Meeting Minutes 2026-06-10 (Minutes), dated June 10, 2026 from Greater Lafourche Port Commission (includes airport). Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Grand Isle Shipyard hold?

Grand Isle Shipyard may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Grand Isle Shipyard's profile

What is Greater Lafourche Port Commission (includes airport) currently buying?

Explore Greater Lafourche Port Commission (includes airport)'s vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Greater Lafourche Port Commission (includes airport)'s profile