CCR Roofing Recommended For Daniel Boone Roof Project
- Disclosed value
- $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35
- From staffreport
- Document date
- May 21, 2026
The 30-second brief
District administration recommends awarding CCR Roofing a construction contract for the Daniel Boone Elementary roof section replacement, with a base bid of $536,287.00 plus a 5% contingency for a total hard cost of $563,101.35. Work will begin after completion of phase II mechanical improvements and is expected to finish by October 23, 2026, funded by the 2027 capital budget.
Ccr Roofing holds this construction contract with Francis Howell R-III School District. Its other public contracts on record include work for Buchanan County R-IV School District and Northeast Vernon County R-I School District.
Term as filed: Construction anticipated to begin after August 1, 2026 and conclude on October 23, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35
- Document date
- May 21, 2026
- Term
- Construction anticipated to begin after August 1, 2026 and conclude on October 23, 2026
- Vendor
- Ccr Roofing
- Source document
- Board of Education Staff Report Daniel Boone Elementary Roof Section Replacement 2026-05-21 (StaffReport)
Ccr Roofing's other public contracts
More Francis Howell R-III School District contracts
Questions about this contract
Who was awarded the construction contract by Francis Howell R-III School District?
Ccr Roofing was awarded this construction contract by Francis Howell R-III School District, as recorded on May 21, 2026. The contract value is $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35.
How much is the Ccr Roofing contract with Francis Howell R-III School District worth?
The Ccr Roofing contract with Francis Howell R-III School District is valued at $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Board of Education Staff Report Daniel Boone Elementary Roof Section Replacement 2026-05-21 (StaffReport), dated May 21, 2026 from Francis Howell R-III School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ccr Roofing hold?
Ccr Roofing may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Francis Howell R-III School District currently buying?
Explore Francis Howell R-III School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.