Southwest Electric Transformer Repair Contract Amended
City of HollandCity · Holland, MI- Disclosed value
- Amendment amount $191,800 with a 10% contingency of $19,000 (total $210,800); new total approved contract amount $356,060
- From agenda
- Document date
- Apr 1, 2026
The 30-second brief
Holland BPW seeks Council approval of a $191,800 contract amendment with Southwest Electric, plus contingency, to repair oil leaks on industrial substation transformers T1 and T2. The change brings the total transformer inspection and repair contract to $356,060, with work to be completed under the existing term through June 30, 2026.
Southwest Electric holds this construction contract with City of Holland. Its other public contracts on record include work for City of Las Vegas and City of Edmond.
Term as filed: Original contract term through June 30, 2026; amendment does not change contract time (271 days total).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Amendment amount $191,800 with a 10% contingency of $19,000 (total $210,800); new total approved contract amount $356,060
- Document date
- April 1, 2026
- Term
- Original contract term through June 30, 2026; amendment does not change contract time (271 days total)
- Vendor
- Southwest Electric
- Agency
- City of Holland
- Source document
- City of Holland City Council Regular Meeting Agenda April 2026 (Agenda)
Southwest Electric's other public contracts
More City of Holland contracts
Questions about this contract
Who was awarded the construction contract by City of Holland?
Southwest Electric was awarded this construction contract by City of Holland, as recorded on April 1, 2026. The contract value is Amendment amount $191,800 with a 10% contingency of $19,000 (total $210,800); new total approved contract amount $356,060.
How much is the Southwest Electric contract with City of Holland worth?
The Southwest Electric contract with City of Holland is valued at Amendment amount $191,800 with a 10% contingency of $19,000 (total $210,800); new total approved contract amount $356,060, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in City of Holland City Council Regular Meeting Agenda April 2026 (Agenda), dated April 1, 2026 from City of Holland. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Southwest Electric hold?
Southwest Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Holland currently buying?
Explore City of Holland's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.