Annex Office Project Cost Increased via Change Orders
Trusted by teams at
Description
The Pella City Council approved three change orders with Christner Contracting, raising the Annex Office Building renovation contract from about $987,000 to $1.49 million. The amendments add water damage remediation, second-floor buildout, and exterior façade work and extend completion to December 31, 2026.
Contract Details
Contract Amount
$986,953.87 original; revised total $1,494,481.47
Vendor
CHRISTNER CONTRACTING
Agency
City of Pella, IA
Contract Type
CONSTRUCTION
Document Date
May 5, 2026
Contract Term
Substantial completion revised to December 31, 2026
Renewal Date
2026-12-31
Renewal Info
Change Order No. 2 extends substantial completion to December 31, 2026 and adds scope for remedial work and second-floor buildout; Change Order No. 3 incorporates façade and brick removal changes approved by the CDC.
More from CHRISTNER CONTRACTING
More from City of Pella
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.