Teton Village Water & Sewer District Meeting Minutes December 2025

Progress Payments to Arco Electric Still Withheld

$276,000 (progress payments being withheld)Teton Village Improvement And Service DistrictARCO ELECTRICDecember 10, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

During discussion of the WWTP Phase IV Plant Expansion, the Board noted that $276,000 in progress payments are currently being withheld by GSE from Arco Electric. The District is evaluating retainage and surety protections to ensure subcontractors are fully paid before final project closeout.

Contract Details

Contract Amount

$276,000 (progress payments being withheld)

Vendor

ARCO ELECTRIC

Agency

Teton Village Improvement And Service District, WY

Contract Type

CONSTRUCTION

Document Date

December 10, 2025

Renewal Info

Subcontract under GSE's bonded WWTP Phase IV contract; payment of withheld progress amounts is contingent on project closeout and District decisions on retainage and surety coverage.