Shred-Kuyrkendall & Associates awarded $1.6M lift station upgrade design contract
St. Charles ParishCounty · Hahnville, LA- Disclosed value
- $1,600,000
- From report
- Document date
- Oct 31, 2025
- Term
- October 14, 2017 – TBD
The 30-second brief
Shred-Kuyrkendall & Associates contracted for $1.6 million design upgrades to Montz/Norco Phase 2 lift stations starting October 14, 2017.
Shredkuyrkendall & Associates holds this design contract with St. Charles Parish.
Term as filed: October 14, 2017 – TBD.
See who signed off on this $1.6M contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Design
- Amount
- $1,600,000
- Document date
- October 31, 2025
- Term
- October 14, 2017 – TBD
- Vendor
- Shredkuyrkendall & Associates
- Agency
- St. Charles Parish
- Source document
- st_charles_parish_capital_projects_wastewater_repo.pdf (Report)
More St. Charles Parish contracts
Questions about this contract
Who was awarded the design contract by St. Charles Parish?
Shredkuyrkendall & Associates was awarded this design contract by St. Charles Parish, as recorded on October 31, 2025. The contract value is $1,600,000.
How much is the Shredkuyrkendall & Associates contract with St. Charles Parish worth?
The Shredkuyrkendall & Associates contract with St. Charles Parish is valued at $1,600,000, covering design work.
What type of contract is this?
This is a Design contract, documented as a report record.
Where was this contract approved?
This contract appears in st_charles_parish_capital_projects_wastewater_repo.pdf (Report), dated October 31, 2025 from St. Charles Parish. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is St. Charles Parish currently buying?
Explore St. Charles Parish's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.