Contractor date extended to March 2026
- Document date
- Mar 4, 2025
The 30-second brief
The contractor has been delayed due to the extremely long lead time for delivery of the Motor Control Center (MCC). Recommends new completion date of March 1, 2026
Evans Contracting holds this contracting contract with Town of Century. Its other public contracts on record include work for Santa Rosa County and City of East Jordan.
See every contract and contact at Town of Century.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Contracting
- Document date
- March 4, 2025
- Term
- NA
- Vendor
- Evans Contracting
- Agency
- Town of Century
- Source document
- town-of-century-council-meeting-agenda-march-4-2025_1d6.pdf (Agenda)
Evans Contracting's other public contracts
More Town of Century contracts
Questions about this contract
Who was awarded the contracting contract by Town of Century?
Evans Contracting was awarded this contracting contract by Town of Century, as recorded on March 4, 2025.
What type of contract is this?
This is a Contracting contract, documented as a agenda record.
Where was this contract approved?
This contract appears in town-of-century-council-meeting-agenda-march-4-2025_1d6.pdf (Agenda), dated March 4, 2025 from Town of Century. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Evans Contracting hold?
Evans Contracting may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Town of Century currently buying?
Explore Town of Century's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.