City of Willmar Awards Construction Contract to Hoffman Construction Co LLC (November 2026)

City of Willmar logoCity of Willmar
Disclosed value
Original contract $122,155.49; Change Order No. 1 -$35,574.50; actual final contract amount $86,580.99; final payment $12,844.14
From agendapacket
Approved
Nov 16, 2026
Term
May 26, 2026 – September 30, 2026

The 30-second brief

What it covers

The City of Willmar accepted Hoffman Construction Co. LLC's completed Project No. 2605-B and approved a $12,844.14 final payment. A $35,574.50 change order reduced the original $122,155.49 contract to a final constructed amount of $86,580.99.

Who holds it

Hoffman Construction Co LLC holds this construction contract with City of Willmar. Its other public contracts on record include work for Centracare- Rice Memorial Hospital.

What happens next

Term as filed: May 26, 2026 – September 30, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Original contract $122,155.49; Change Order No. 1 -$35,574.50; actual final contract amount $86,580.99; final payment $12,844.14
Document date
November 16, 2026
Term
May 26, 2026 – September 30, 2026
Source document
City of Willmar AgendaPacket November 16, 2026 (AgendaPacket)

Hoffman Construction Co LLC's other public contracts

More City of Willmar contracts

Questions about this contract

Who was awarded the construction contract by City of Willmar?

Hoffman Construction Co LLC was awarded this construction contract by City of Willmar, as recorded on November 16, 2026. The contract value is Original contract $122,155.49; Change Order No. 1 -$35,574.50; actual final contract amount $86,580.99; final payment $12,844.14.

How much is the Hoffman Construction Co LLC contract with City of Willmar worth?

The Hoffman Construction Co LLC contract with City of Willmar is valued at Original contract $122,155.49; Change Order No. 1 -$35,574.50; actual final contract amount $86,580.99; final payment $12,844.14, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Willmar AgendaPacket November 16, 2026 (AgendaPacket), dated November 16, 2026 from City of Willmar. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Hoffman Construction Co LLC hold?

Hoffman Construction Co LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Willmar currently buying?

Explore City of Willmar's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo