CONSTRUCTIONAMENDED

WWTP Phase 2 Change Order Raises Miron Contract

The City of Sault Ste. Marie issued Change Order No. 009 to Miron Construction Co., Inc. for $84,449.01 on the WWTP Improvements Phase 2 project. The amendment raises the contract to $23,840,463.10 without extending the May 9, 2027 substantial-completion or July 8, 2027 final-payment dates.

Document date · September 21, 2026

Track City of Sault Ste. Marie contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Sault Ste. Marie.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Net increase of this Change Order: $84,449.01; revised contract price: $23,840,463.10
Contract type
CONSTRUCTION
Contract term
Substantial Completion: May 9, 2027; Ready for Final Payment: July 8, 2027; no change in contract times
Renewal date
2027-07-08
Renewal
Change Order No. 009 adds $84,449.01 to the contract and states that it becomes an amendment subject to the existing contract terms. No additional time compensation is provided.
Document type
Contract
Source document
City of Sault Ste. Marie Contract Change Order 009 WWTP Improvements Phase 2 2026-09-22

Related contracts

Other contracts from Miron Construction Company Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Sault Ste. Marie?

Miron Construction Company Inc was awarded this construction contract by City of Sault Ste. Marie, as recorded on September 21, 2026. The contract value is Net increase of this Change Order: $84,449.01; revised contract price: $23,840,463.10.

How much is the Miron Construction Company Inc contract with City of Sault Ste. Marie worth?

The Miron Construction Company Inc contract with City of Sault Ste. Marie is valued at Net increase of this Change Order: $84,449.01; revised contract price: $23,840,463.10, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in City of Sault Ste. Marie Contract Change Order 009 WWTP Improvements Phase 2 2026-09-22 (Contract), dated September 21, 2026 from City of Sault Ste. Marie. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Miron Construction Company Inc hold?

Miron Construction Company Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Miron Construction Company Inc's profile

What is City of Sault Ste. Marie currently buying?

Explore City of Sault Ste. Marie's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Sault Ste. Marie's profile