WWTP Improvements Change Order Awarded to Miron Construction

The City of Sault Ste. Marie amended Miron Construction Co., Inc.’s WWTP Improvements Phase 1 contract through Change Order No. 015. The change adds $21,866.44 for duct, fire alarm, and sampler piping modifications, bringing the revised contract price to $24,208,900.29 and extending final payment readiness to January 16, 2027.

Document date · September 21, 2026

Track City of Sault Ste. Marie contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Sault Ste. Marie.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Net increase of $21,866.44; revised contract price $24,208,900.29
Contract type
CONSTRUCTION
Contract term
Commencement of contract time: September 17, 2024; revised substantial completion: November 17, 2026; revised ready for final payment: January 16, 2027
Renewal date
2027-01-16
Renewal
Change Order No. 015 is incorporated as an amendment to the existing construction contract. No additional contract days were authorized; revised substantial completion is November 17, 2026, with final payment readiness on January 16, 2027.
Document type
Contract
Source document
City of Sault Ste. Marie Contract Change Order 015 2026-09-22

Related contracts

Other contracts from Miron Construction Company Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Sault Ste. Marie?

Miron Construction Company Inc was awarded this construction contract by City of Sault Ste. Marie, as recorded on September 21, 2026. The contract value is Net increase of $21,866.44; revised contract price $24,208,900.29.

How much is the Miron Construction Company Inc contract with City of Sault Ste. Marie worth?

The Miron Construction Company Inc contract with City of Sault Ste. Marie is valued at Net increase of $21,866.44; revised contract price $24,208,900.29, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in City of Sault Ste. Marie Contract Change Order 015 2026-09-22 (Contract), dated September 21, 2026 from City of Sault Ste. Marie. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Miron Construction Company Inc hold?

Miron Construction Company Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Miron Construction Company Inc's profile

What is City of Sault Ste. Marie currently buying?

Explore City of Sault Ste. Marie's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Sault Ste. Marie's profile