CONSTRUCTIONPENDING

LHC Subcontracted for Tank Project Site Work

Preload, LLC’s change order pricing for the Lower Zone Storage Tank 2 Replacement Project includes subcontracted services from LHC for erosion control, SWPPP extensions, mobilization, and spring site restoration. These LHC tasks support the revised construction schedule under the various winter shutdown options considered by the City.

Document date · June 15, 2026

Track City of Kalispell contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Kalispell.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Included within Option 1 and Option 2 cost breakdowns (e.g., $27,400 for erosion control and mobilization; $12,000 for laydown/access roads refresh)
Contract type
CONSTRUCTION
Contract term
Work tied to 2026–2027 construction seasons for site work and erosion control during winter shutdown scenarios
Renewal
Subcontracted work is embedded within Preload, LLC’s contract pricing and will proceed according to the winter shutdown option chosen by the City; no separate renewal schedule is specified.
Document type
Agenda
Source document
City of Kalispell Agenda 2026-06-15

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Kalispell?

LHC was awarded this construction contract by City of Kalispell, as recorded on June 15, 2026. The contract value is Included within Option 1 and Option 2 cost breakdowns (e.g., $27,400 for erosion control and mobilization; $12,000 for laydown/access roads refresh).

How much is the LHC contract with City of Kalispell worth?

The LHC contract with City of Kalispell is valued at Included within Option 1 and Option 2 cost breakdowns (e.g., $27,400 for erosion control and mobilization; $12,000 for laydown/access roads refresh), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Kalispell Agenda 2026-06-15 (Agenda), dated June 15, 2026 from City of Kalispell. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does LHC hold?

LHC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View LHC's profile