CONSTRUCTIONRECOMMENDED

Nabholz MLK Utility Relocation Contract Change Approved

Fayetteville staff recommend City Council approval of Change Order No. 3 to the Nabholz Construction contract for MLK utility relocations, increasing the contract by $687,340.18 to cover unforeseen parking lot and drive aisle restoration costs. Under the ARDOT Relocation Agreement, ARDOT will fund most of the change while the City contributes approximately $90,770.23.

Status
RECOMMENDED
Document date
August 11, 2026
Contract type
CONSTRUCTION
Vendor
Nabholz Construction
Agency
City of Fayetteville · AR

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$687,340.18 (Change Order No. 3 increase; additional $330,554.38 beyond contingency; total Relocation Agreement $25,294,663.64)
Contract type
CONSTRUCTION
Contract term
Original MLK utility relocation contract approved April 2025; change order for end-of-project reconciliation
Renewal
This is Change Order No. 3 to the April 2025 contract under Resolution 101‑25; prior change orders addressed waterline realignment and service connections. The overall ARDOT Relocation Agreement (latest CO No. 5) is expected to reconcile about $850,000 under the original estimate.
Document type
Agenda
Source document
City of Fayetteville Water, Sewer, and Solid Waste Committee Agenda 2026-08-11

Related contracts

Other contracts from Nabholz Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Fayetteville?

Nabholz Construction was awarded this construction contract by City of Fayetteville, as recorded on August 11, 2026. The contract value is $687,340.18 (Change Order No. 3 increase; additional $330,554.38 beyond contingency; total Relocation Agreement $25,294,663.64).

How much is the Nabholz Construction contract with City of Fayetteville worth?

The Nabholz Construction contract with City of Fayetteville is valued at $687,340.18 (Change Order No. 3 increase; additional $330,554.38 beyond contingency; total Relocation Agreement $25,294,663.64), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Fayetteville Water, Sewer, and Solid Waste Committee Agenda 2026-08-11 (Agenda), dated August 11, 2026 from City of Fayetteville. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Nabholz Construction hold?

Nabholz Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Nabholz Construction's profile

What is City of Fayetteville currently buying?

Explore City of Fayetteville's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Fayetteville's profile