CONSTRUCTIONAMENDED

Effingham sewer contract amended via Change Order No. 3

The City of Effingham approved Change Order No. 3 with A & R Mechanical for the Mt. Vernon Avenue Sanitary Sewer project, increasing the overall contract by $12,789.00 to a new total of $630,046.59. The amendment rebalances quantities across sewer, paving, and related work based on field conditions, with Section A increasing and Section B decreasing for a net overall increase.

Status
AMENDED
Document date
April 22, 2026
Contract type
CONSTRUCTION
Vendor
A & R Mechanical
Agency
City of Effingham city · IL

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Increase of $12,789.00 (new total $630,046.59; Section A current $401,390.09; Section B current $228,656.50)
Contract type
CONSTRUCTION
Renewal
This is Change Order No. 3 to Contract 25008.7, following prior Change Orders No. 1 and No. 2, and adjusts unit-price quantities for various sewer and related items, resulting in a revised total contract amount of $630,046.59 (Section A $401,390.09; Section B $228,656.50). No change to contract time is explicitly stated in this document.
Document type
Contract
Source document
City of Effingham Change Order No. 3 Sanitary Sewer Improvements 2026-04-22

Related contracts

Other contracts from A & R Mechanical.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Effingham city?

A & R Mechanical was awarded this construction contract by City of Effingham city, as recorded on April 22, 2026. The contract value is Increase of $12,789.00 (new total $630,046.59; Section A current $401,390.09; Section B current $228,656.50).

How much is the A & R Mechanical contract with City of Effingham city worth?

The A & R Mechanical contract with City of Effingham city is valued at Increase of $12,789.00 (new total $630,046.59; Section A current $401,390.09; Section B current $228,656.50), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in City of Effingham Change Order No. 3 Sanitary Sewer Improvements 2026-04-22 (Contract), dated April 22, 2026 from City of Effingham city. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does A & R Mechanical hold?

A & R Mechanical may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View A & R Mechanical's profile

What is City of Effingham city currently buying?

Explore City of Effingham city's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Effingham city's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 100,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free