CONSTRUCTIONAMENDED

City Approves $12M Blue Jays Complex Change Order

Dunedin City Commission adopted Resolution 19-45 approving Spring Training Change Order No. 16 with the Toronto Blue Jays, appropriating $12,085,939 for additional work at the Player Development Complex. Under the existing 25-year agreement, the Club is responsible for project costs exceeding the original $81 million budget, with total project costs now projected at over $103 million.

Document date · September 5, 2019

Track City of Dunedin contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Dunedin.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$12,085,939 (Change Order No. 16); total project budget $81,000,000; current total cost approx. $103,000,000
Contract type
CONSTRUCTION
Contract term
25-year license agreement; construction agreement dated November 2, 2017
Renewal date
2042-11-02
Renewal
Construction and renovation agreement between the City and Toronto Blue Jays dated November 2, 2017, tied to a 25-year license agreement; Club is responsible for costs exceeding the original $81 million project budget.
Document type
Minutes
Source document
city-of-dunedin-minutes-ev-charging-stations-green-building-standards-sep-5-2019_1d4.pdf

Related contracts

Other contracts from Toronto Blue Jays.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Dunedin?

Toronto Blue Jays was awarded this construction contract by City of Dunedin, as recorded on September 5, 2019. The contract value is $12,085,939 (Change Order No. 16); total project budget $81,000,000; current total cost approx. $103,000,000.

How much is the Toronto Blue Jays contract with City of Dunedin worth?

The Toronto Blue Jays contract with City of Dunedin is valued at $12,085,939 (Change Order No. 16); total project budget $81,000,000; current total cost approx. $103,000,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in city-of-dunedin-minutes-ev-charging-stations-green-building-standards-sep-5-2019_1d4.pdf (Minutes), dated September 5, 2019 from City of Dunedin. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Toronto Blue Jays hold?

Toronto Blue Jays may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Toronto Blue Jays's profile

What is City of Dunedin currently buying?

Explore City of Dunedin's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Dunedin's profile