Septic System Contract at Town Hall Remains Incomplete
Trusted by teams at
Description
The Town of Crystal Bay has an ongoing construction contract with Eric for septic system installation at the Town Hall, with $30,000 paid of a $55,000 total and additional payments pending proper invoicing and project completion. The agreement includes legal provisions for liquidated damages due to delays, and any future change orders are subject to legal review.
Contract Details
Contract Amount
$30,000 (of $55,000 total), with possible $25,000 remaining
Vendor
ERIC
Agency
Town of Crystal Bay, MN
Contract Type
CONSTRUCTION
Document Date
December 16, 2025
Renewal Date
2026-08-01
Renewal Info
No further payments until receipt of correct invoice; liquidated damages accrue for delays. Contract may be amended for change orders with legal oversight. Remaining $25,000 is contingent on resolving outstanding billing and project completion.
More from ERIC
More from Town of Crystal Bay
Town of Crystal Bay Minutes Regular Board Meeting 2026-04-21
Town of Crystal Bay Minutes Regular Board Meeting 2026-04-21
Town of Crystal Bay Minutes Regular Board Meeting 2026-04-21
Town of Crystal Bay Minutes Regular Board Meeting 2026-04-21
Town of Crystal Bay Minutes Regular Board Meeting 2026-04-21
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.