CONTRACTAMENDED

Port Moves to Increase Contingency on Cushman Dock Contract

Santa Cruz Port District
Disclosed value
$9,456,920 (contingency increased by $750,000; revised total construction cost $11,625,458)
From minutes
Document date
Mar 24, 2026
Renews
Free account

The 30-second brief

What it covers

After awarding the G & X Dock reconstruction contract to Cushman Contracting, the Santa Cruz Port District sought authorization to increase project contingency by $750,000, bringing the total construction budget to $11,625,458. The added funds address significant scope refinements including stronger dock systems, electrical changes, and longer piles.

Who holds it

Cushman Contracting holds this construction contract with Santa Cruz Port District. Its other public contracts on record include work for Cachuma Operation and Maintenance Board.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every Santa Cruz Port District contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$9,456,920 (contingency increased by $750,000; revised total construction cost $11,625,458)
Document date
March 24, 2026
Term
Construction window June 15, 2026 – November 30, 2026
Renews
Free account
Source document
Santa Cruz Port Commission Minutes March 2026 (Minutes)

Cushman Contracting's other public contracts

More Santa Cruz Port District contracts

Questions about this contract

Who was awarded the construction contract by Santa Cruz Port District?

Cushman Contracting was awarded this construction contract by Santa Cruz Port District, as recorded on March 24, 2026. The contract value is $9,456,920 (contingency increased by $750,000; revised total construction cost $11,625,458).

How much is the Cushman Contracting contract with Santa Cruz Port District worth?

The Cushman Contracting contract with Santa Cruz Port District is valued at $9,456,920 (contingency increased by $750,000; revised total construction cost $11,625,458), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Santa Cruz Port Commission Minutes March 2026 (Minutes), dated March 24, 2026 from Santa Cruz Port District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Cushman Contracting hold?

Cushman Contracting may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Santa Cruz Port District currently buying?

Explore Santa Cruz Port District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →