CONTRACTONGOING

HEI Continues ARPA Drinking Water Construction With Change Orders

Brushy Creek Mud logoBrushy Creek Mud
Disclosed value
$3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6)
From agenda
Document date
Aug 13, 2026

The 30-second brief

What it covers

HEI is constructing ARPA Drinking Water Source & Treatment improvements under a $3.16 million contract with multiple change orders and a substantial completion deadline of August 3, 2026. The contractor has requested a 12‑week extension to finish emergency power and winterization upgrades at District facilities.

Who holds it

HEI holds this construction contract with Brushy Creek Mud. Its other public contracts on record include work for Pikes Peak Rural Transportation Authority and Red Lake Watershed District.

What happens next

Term as filed: Substantial completion no later than August 3, 2026 (per contract).

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6)
Document date
August 13, 2026
Term
Substantial completion no later than August 3, 2026 (per contract)
Vendor
HEI
Source document
Brushy Creek Municipal Utility District Agenda Utilities Infrastructure Advisory Committee Meeting 2026-08-17 (Agenda)

HEI's other public contracts

More Brushy Creek Mud contracts

Questions about this contract

Who was awarded the construction contract by Brushy Creek Mud?

HEI was awarded this construction contract by Brushy Creek Mud, as recorded on August 13, 2026. The contract value is $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6).

How much is the HEI contract with Brushy Creek Mud worth?

The HEI contract with Brushy Creek Mud is valued at $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Brushy Creek Municipal Utility District Agenda Utilities Infrastructure Advisory Committee Meeting 2026-08-17 (Agenda), dated August 13, 2026 from Brushy Creek Mud. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does HEI hold?

HEI may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Brushy Creek Mud currently buying?

Explore Brushy Creek Mud's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →