HEI Continues ARPA Drinking Water Construction With Change Orders
- Disclosed value
- $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6)
- From agenda
- Document date
- Aug 13, 2026
The 30-second brief
HEI is constructing ARPA Drinking Water Source & Treatment improvements under a $3.16 million contract with multiple change orders and a substantial completion deadline of August 3, 2026. The contractor has requested a 12‑week extension to finish emergency power and winterization upgrades at District facilities.
HEI holds this construction contract with Brushy Creek Mud. Its other public contracts on record include work for Pikes Peak Rural Transportation Authority and Red Lake Watershed District.
Term as filed: Substantial completion no later than August 3, 2026 (per contract).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6)
- Document date
- August 13, 2026
- Term
- Substantial completion no later than August 3, 2026 (per contract)
- Vendor
- HEI
- Agency
- Brushy Creek Mud
- Source document
- Brushy Creek Municipal Utility District Agenda Utilities Infrastructure Advisory Committee Meeting 2026-08-17 (Agenda)
HEI's other public contracts
More Brushy Creek Mud contracts
Questions about this contract
Who was awarded the construction contract by Brushy Creek Mud?
HEI was awarded this construction contract by Brushy Creek Mud, as recorded on August 13, 2026. The contract value is $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6).
How much is the HEI contract with Brushy Creek Mud worth?
The HEI contract with Brushy Creek Mud is valued at $3,160,509 (original contract); Change Orders: -$82,305 (CO1), $2,616.91 (CO2), $3,421.06 (CO3), -$335,915.45 (CO4), $59,540.99 (CO5), $37,371.98 (CO6), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Brushy Creek Municipal Utility District Agenda Utilities Infrastructure Advisory Committee Meeting 2026-08-17 (Agenda), dated August 13, 2026 from Brushy Creek Mud. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does HEI hold?
HEI may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Brushy Creek Mud currently buying?
Explore Brushy Creek Mud's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.