CONSTRUCTIONRECOMMENDED

Popco Change Order Recommended For Generator Project

The Commission staff recommended a $62,023 negotiated Change Order No. 2 with Popco, Inc. for the FEMA fixed generator installation project. The action extends Substantial Completion through October 21, 2026 and authorizes JWSC personnel to install six SCADA panels, with JWSC costs set off against Popco's payment up to $15,000 without prior written approval.

Document date · October 12, 2026

Track Brunswick-Glynn Joint Water And Sewer Commission contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Brunswick-Glynn Joint Water And Sewer Commission.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$62,023; JWSC labor and material setoff for SCADA installation estimated below $15,000 and capped at $15,000 without Popco's prior written approval
Contract type
CONSTRUCTION
Contract term
Substantial Completion extended through October 21, 2026; Final Completion due within 30 days after Substantial Completion
Renewal date
2026-10-21
Renewal
Change Order No. 2 extends Substantial Completion through October 21, 2026, with Final Completion due within 30 days thereafter. The change order is effective only after Board approval and execution by the parties.
Document type
StaffReport
Source document
Brunswick-Glynn Joint Water and Sewer Commission StaffReport Change Order No. 2 - FEMA-Funded Generator Installation 2026-10-15

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Brunswick-Glynn Joint Water And Sewer Commission?

Popco Inc was awarded this construction contract by Brunswick-Glynn Joint Water And Sewer Commission, as recorded on October 12, 2026. The contract value is $62,023; JWSC labor and material setoff for SCADA installation estimated below $15,000 and capped at $15,000 without Popco's prior written approval.

How much is the Popco Inc contract with Brunswick-Glynn Joint Water And Sewer Commission worth?

The Popco Inc contract with Brunswick-Glynn Joint Water And Sewer Commission is valued at $62,023; JWSC labor and material setoff for SCADA installation estimated below $15,000 and capped at $15,000 without Popco's prior written approval, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Brunswick-Glynn Joint Water and Sewer Commission StaffReport Change Order No. 2 - FEMA-Funded Generator Installation 2026-10-15 (StaffReport), dated October 12, 2026 from Brunswick-Glynn Joint Water And Sewer Commission. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Popco Inc hold?

Popco Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Popco Inc's profile

What is Brunswick-Glynn Joint Water And Sewer Commission currently buying?

Explore Brunswick-Glynn Joint Water And Sewer Commission's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Brunswick-Glynn Joint Water And Sewer Commission's profile