Town of Albion Awards Construction Contract to Statewide Aquastore Inc (December 2025)
- Disclosed value
- $68,206.09 (final closeout payment); original contract price and total completed work exceed $1.5 million (summary indicates cumulative work and change orders)
- From report
- Approved
- Dec 19, 2025
- Renews
- Free account
The 30-second brief
The Village of Albion is recommended to approve the final closeout payment of $68,206.09 to Statewide Aquastore Inc. for the Water Tank Replacement Project, with all contract work completed and a two-year warranty commencing from December 19, 2025. This payment represents full release of retention monies and contract closeout.
Statewide Aquastore Inc holds this construction contract with Town of Albion. Its other public contracts on record include work for Denmark Wd 1 and Unionville village.
The renewal date is on record. A free account shows it, with the renewals for every Town of Albion contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $68,206.09 (final closeout payment); original contract price and total completed work exceed $1.5 million (summary indicates cumulative work and change orders)
- Document date
- December 19, 2025
- Term
- Contract completed; work finished under contract terms; 2-year warranty to remain in effect post-completion as of December 19, 2025
- Renews
- Free account
- Vendor
- Statewide Aquastore Inc
- Agency
- Town of Albion
- Source document
- Village of Albion Water Tank Replacement Project Report December 2025 (Report)
Statewide Aquastore Inc's other public contracts
More Town of Albion contracts
Questions about this contract
Who was awarded the construction contract by Town of Albion?
Statewide Aquastore Inc was awarded this construction contract by Town of Albion, as recorded on December 19, 2025. The contract value is $68,206.09 (final closeout payment); original contract price and total completed work exceed $1.5 million (summary indicates cumulative work and change orders).
How much is the Statewide Aquastore Inc contract with Town of Albion worth?
The Statewide Aquastore Inc contract with Town of Albion is valued at $68,206.09 (final closeout payment); original contract price and total completed work exceed $1.5 million (summary indicates cumulative work and change orders), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Village of Albion Water Tank Replacement Project Report December 2025 (Report), dated December 19, 2025 from Town of Albion. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Statewide Aquastore Inc hold?
Statewide Aquastore Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Albion currently buying?
Explore Town of Albion's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.