Manchester School District Priority One Projects OPM Monthly Project Report October 2025

Excavation Progress Payment for Hillside School Project

$3,748,466.00 (contract sum after change orders; October 2025 application: $364,166.25)Manchester School DistrictWILLIAM P DAVIS EXCAVATION LLCOctober 31, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

William P Davis Excavation LLC received a $364,166.25 October progress payment for sitework at Hillside Middle School under a total contract of $3.75 million.

Contract Details

Contract Amount

$3,748,466.00 (contract sum after change orders; October 2025 application: $364,166.25)

Vendor

WILLIAM P DAVIS EXCAVATION LLC

Agency

Manchester School District, NH

Contract Type

CONSTRUCTION

Document Date

October 31, 2025

Contract Term

Sitework contract for Hillside Middle School; contract date May 26, 2025; application through October 31, 2025

Renewal Date

2026-07-31

Renewal Info

Progress billing against lump-sum contract, including approved change orders; contract ends at project completion.