Sewer Project Change Order Cites Rail Pros Costs

Borough of BellwoodRAIL PROSNovember 25, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Change Order #4 for the Sanitary Sewer Project includes relocating sewer work off Norfolk Southern property partly due to cost and coordination issues involving consultant Rail Pros. The change order increases project cost and extends substantial completion by 56 days and final completion by 147 days; the prime contractor is not named in the agenda.

Contract Details

Vendor

RAIL PROS

Agency

Borough of Bellwood, PA

Contract Type

CONSTRUCTION

Document Date

November 25, 2025

Contract Term

56-day extension for Substantial Completion and 147-day extension for Final Completion (underlying construction contract)

Renewal Info

Change Order #4 modifies the existing construction contract by relocating the alignment and extending contract time by 56 days for substantial completion and 147 days for final completion.