City of Chowchilla Agenda 2026-05-26

City Closeout of Well and Generator Projects

$1,190,560.00 (original contract) + $33,514.00 (change orders); total construction cost $1,242,675.00; release of 5% retention $61,203.75City of ChowchillaW.M. LYLES COMPANYMay 26, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Chowchilla is moving to accept work completed by W.M. Lyles Company for the Well 15 development, water tank backup generators, and Civic Center generator projects and to file Notices of Completion. The construction contract of $1,190,560, plus change orders and testing, totals $1,242,675, with 5% retention to be released after the statutory period.

Contract Details

Contract Amount

$1,190,560.00 (original contract) + $33,514.00 (change orders); total construction cost $1,242,675.00; release of 5% retention $61,203.75

Vendor

W.M. LYLES COMPANY

Agency

City of Chowchilla, CA

Contract Type

CONSTRUCTION

Document Date

May 26, 2026

Contract Term

Agreement dated November 12, 2024; construction completed by April 2026

Renewal Date

2026-05-31

Renewal Info

One-time construction projects; Notices of Completion to be recorded and 5% retention released after a 35-day holding period; no renewal terms.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free