CONSTRUCTIONAMENDED

La Porte Redevelopment Authority Agenda Packet 2026-06-11

Landmark Construction Change Order Expands Detention Basin Scope

$625,859.00 (original); Change Order No. 1 for $269,879.00 (new total $895,738.00)LA PORTE AREA WATER AUTHORITYLANDMARK CONSTRUCTIONJune 11, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

La Porte Redevelopment Authority plans to approve Change Order No. 1 with Landmark Construction for the Lakes at Fairmont Greens Detention project, adding $269,879 and 60 days for additional pond excavation. The new total contract value will be $895,738, with project completion now set for August 16, 2026.

Contract Details

Contract Amount

$625,859.00 (original); Change Order No. 1 for $269,879.00 (new total $895,738.00)

Vendor

LANDMARK CONSTRUCTION

Agency

LA PORTE AREA WATER AUTHORITY, TX

Contract Type

CONSTRUCTION

Document Date

June 11, 2026

Contract Term

Original: 90 days from March 19, 2026; Amended: 150 days (new completion August 16, 2026)

Renewal Date

2026-08-16

Renewal Info

Amended via Change Order No. 1 on June 3, 2026, which adds $269,879 and 60 days. No previous change orders.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free