Faber Construction Receives Change Order, Fisherman's Harbor Project Closed
Trusted by teams at
Description
The Port Commission approved a $165,064 change order and final settlement agreement with Faber Construction for Fisherman's Harbor retail development, increasing schedule and value. The contract was finalized at $14 million after project delays and negotiations.
Contract Details
Contract Amount
$165,064 (change order); $14,001,738.52 (final contract value)
Vendor
FABER CONSTRUCTION
Agency
Port Of Everett, WA
Contract Type
CONSTRUCTION
Document Date
May 12, 2026
Contract Term
Additional 161 calendar days for Substantial Completion; 180 days for punchlist completion
Renewal Date
2026-05-12
Renewal Info
Closeout; Change Order No. 1 extended schedule and increased contract. Project now complete, no further renewals.
More from FABER CONSTRUCTION
More from Port Of Everett
Everett Port Commission Agenda Item Cover Sheet Interlocal Cooperative Purchasing Agreement – Kitsap County 2026-06-04
Everett Port Commission StaffReport Property, Cyber and Crime Insurance Policy Renewal 2026-06-04
Everett Port Commission StaffReport Property, Cyber and Crime Insurance Policy Renewal 2026-06-04
Everett Port Commission Agenda 2026-06-04
Everett Port Commission Agenda 2026-06-04
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.