Elgin Adds Funds for Spring Street Deck Repairs
- Disclosed value
- $87,385 (change order); revised contract total $286,760
- From agenda
- Document date
- Dec 17, 2025
The 30-second brief
Elgin will approve Change Order No. 1 with Golf Construction for Bid 25-043, adding $87,385 to address unforeseen broken tendons and extra concrete repairs at the Spring Street parking deck. The total contract for parking structure repairs and painting will increase to $286,760, with work now expected to finish by April 2026.
Golf Construction holds this facilities contract with City of Elgin city. Its other public contracts on record include work for John H Stroger Jr Hospital and Town of Normal town.
Term as filed: Original 2025 project with work extended to anticipated completion by end of April 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Facilities
- Amount
- $87,385 (change order); revised contract total $286,760
- Document date
- December 17, 2025
- Term
- Original 2025 project with work extended to anticipated completion by end of April 2026
- Vendor
- Golf Construction
- Agency
- City of Elgin city
- Source document
- city_council_committee_of_the_whole_meeting_agenda.pdf (Agenda)
Golf Construction's other public contracts
More City of Elgin city contracts
Questions about this contract
Who was awarded the facilities contract by City of Elgin city?
Golf Construction was awarded this facilities contract by City of Elgin city, as recorded on December 17, 2025. The contract value is $87,385 (change order); revised contract total $286,760.
How much is the Golf Construction contract with City of Elgin city worth?
The Golf Construction contract with City of Elgin city is valued at $87,385 (change order); revised contract total $286,760, covering facilities work.
What type of contract is this?
This is a Facilities contract, documented as a agenda record.
Where was this contract approved?
This contract appears in city_council_committee_of_the_whole_meeting_agenda.pdf (Agenda), dated December 17, 2025 from City of Elgin city. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Golf Construction hold?
Golf Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Elgin city currently buying?
Explore City of Elgin city's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.