CONSTRUCTIONAMENDED

Mason approves sewer rehab change order with Vortex

The Town of Mason approved Change Order No. 2 with Vortex Companies for the Sanitary Sewer System Rehabilitation project, adjusting final quantities and adding wet well rehabilitation and 4-inch force main installation. The change order decreases the contract amount by $3,539.84 to a final total of $251,851.16 and extends substantial completion to May 10, 2026.

Document date · April 18, 2026

Track Town of Mason contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Town of Mason.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$255,391.00 (original contract); Change Order No. 2 decrease $3,539.84; final contract $251,851.16
Contract type
CONSTRUCTION
Contract term
Notice to Proceed: November 10, 2025; Substantial Completion extended to May 10, 2026; Final Payment date extended to May 25, 2026
Renewal date
2026-05-25
Renewal
Original contract times of 90 days to substantial completion and 105 days to final payment from the November 10, 2025 NTP were previously adjusted; Change Order No. 2 adds 30 days to both milestones, setting substantial completion at May 10, 2026 and final payment at May 25, 2026, and revises the total contract price downward to $251,851.16 based on final quantities and added scope.
Document type
Contract
Source document
Town of Mason Change Order 2 Sanitary Sewer System Rehabilitation April 2026

Related contracts

Other contracts from Vortex Companies.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Mason?

Vortex Companies was awarded this construction contract by Town of Mason, as recorded on April 18, 2026. The contract value is $255,391.00 (original contract); Change Order No. 2 decrease $3,539.84; final contract $251,851.16.

How much is the Vortex Companies contract with Town of Mason worth?

The Vortex Companies contract with Town of Mason is valued at $255,391.00 (original contract); Change Order No. 2 decrease $3,539.84; final contract $251,851.16, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Town of Mason Change Order 2 Sanitary Sewer System Rehabilitation April 2026 (Contract), dated April 18, 2026 from Town of Mason. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Vortex Companies hold?

Vortex Companies may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Vortex Companies's profile

What is Town of Mason currently buying?

Explore Town of Mason's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Mason's profile