CONSTRUCTIONAMENDED

city-of-box-elder-staff-report-2024-10-30_6a7.pdf

Hotel Way Construction Change Order Approved for Dream Construction

$70,113.15 (increase), new total $2,832,981.25City of Box ElderDREAM CONSTRUCTIONOctober 30, 2024

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

City Council is set to approve Change Order No. 2 to the Hotel Way Construction Project with Dream Construction, adding $70,113.15 for work extended into 2025, raising the contract total to $2,832,981.25 and extending the timeline to May 30, 2025. The adjustment reflects higher unit prices for work delayed due to slow railroad right of way access.

Contract Details

Contract Amount

$70,113.15 (increase), new total $2,832,981.25

Vendor

DREAM CONSTRUCTION

Agency

City of Box Elder, SD

Contract Type

CONSTRUCTION

Document Date

October 30, 2024

Contract Term

Contract completion extended to May 30, 2025

Renewal Date

2025-05-30

Renewal Info

Change Order No. 2 increases value and extends duration; original contract awarded Feb 4, 2024, prior Change Order 1 approved Sept 17, 2024 for $13,760. No automatic renewal; end date amended to May 30, 2025.