HB Foundations Slated for Next Phase of Redvers WTP Work
Town of RedversCity · Redvers, SK- Document date
- Jun 8, 2026
- Term
- Planned tasks week of June 15-21, 2026
The 30-second brief
HB Foundations is scheduled to commence foundational and concrete bracing and pouring activities at the Redvers WTP Upgrade project during the week of June 15-21, 2026. This represents planned engagement for the next phase of construction.
Hb Foundations holds this construction contract with Town of Redvers.
Term as filed: Planned tasks week of June 15-21, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- June 8, 2026
- Term
- Planned tasks week of June 15-21, 2026
- Vendor
- Hb Foundations
- Agency
- Town of Redvers
- Source document
- Redvers WTP Upgrade Weekly Report # 8 June 8 - June 12, 2026 (Report)
Hb Foundations's other public contracts
More Town of Redvers contracts
Questions about this contract
Who was awarded the construction contract by Town of Redvers?
Hb Foundations was awarded this construction contract by Town of Redvers, as recorded on June 8, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Redvers WTP Upgrade Weekly Report # 8 June 8 - June 12, 2026 (Report), dated June 8, 2026 from Town of Redvers. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Hb Foundations hold?
Hb Foundations may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Town of Redvers currently buying?
Explore Town of Redvers's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.