Oregon Tech Finance, Facilities & Audit Committee Agenda Packet 2026-06-03

Campus Booster Station Construction Nears Completion

Construction budget $1,405,306 within total project budget $2,967,006; change orders totaling $382,016 (CO 1 $22,725; CO 2 $340,511; CO 3 $18,780)Oregon Institute Of TechnologyBOGATAY CONSTRUCTIONJune 3, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Bogatay Construction is installing Oregon Tech’s new campus booster station and 12‑inch water line under a $1.4 million construction budget. The project, revised to $2.97 million total, is scheduled for completion by the end of May 2026.

Contract Details

Contract Amount

Construction budget $1,405,306 within total project budget $2,967,006; change orders totaling $382,016 (CO 1 $22,725; CO 2 $340,511; CO 3 $18,780)

Vendor

BOGATAY CONSTRUCTION

Agency

Oregon Institute Of Technology, OR

Contract Type

CONSTRUCTION

Document Date

June 3, 2026

Contract Term

Construction underway with project completion scheduled May 31, 2026

Renewal Date

2026-05-31

Renewal Info

Construction contract adjusted through at least three change orders; no long‑term renewal options beyond project completion are described.

More from BOGATAY CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free