Second change order increases KIWWTP electrical contract
Trusted by teams at
Description
Lehigh County Authority plans to approve a $109,481.89 Electrical Construction Change Order 02 with Philips Brothers Electrical Contractors, Inc. for KIWWTP Substation 1 and primary switchgear. The change covers increased PPL-related costs, directional drilling, and installation of a new manhole, bringing the electrical contract total to $5,088,960.15 without extending the schedule.
Contract Details
Contract Amount
$109,481.89
Vendor
PHILIPS BROTHERS ELECTRICAL CONTRACTORS INC
Agency
Lehigh county Housing Authority, PA
Contract Type
CONSTRUCTION
Document Date
September 22, 2025
Contract Term
Substantial completion January 20, 2026; final payment readiness March 22, 2026 (unchanged)
Renewal Date
2026-03-22
Renewal Info
Change Order EC-02 increases the electrical contract from $4,979,478.26 to $5,088,960.15; contract times remain substantial completion January 20, 2026 and final payment March 22, 2026.
More from PHILIPS BROTHERS ELECTRICAL CONTRACTORS INC
More from Lehigh county Housing Authority
Lehigh County Authority AgendaPacket Board Meeting 2026-06-08
Lehigh County Authority AgendaPacket Board Meeting 2026-06-08
Lehigh County Authority AgendaPacket Board Meeting 2026-06-08
Lehigh County Authority AgendaPacket Board Meeting 2026-06-08
Lehigh County Authority AgendaPacket Board Meeting 2026-06-08
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.