lehigh_county_authority_board_meeting_agenda_septe.pdf

Second change order increases KIWWTP electrical contract

$109,481.89Lehigh county Housing AuthorityPHILIPS BROTHERS ELECTRICAL CONTRACTORS INCSeptember 22, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Lehigh County Authority plans to approve a $109,481.89 Electrical Construction Change Order 02 with Philips Brothers Electrical Contractors, Inc. for KIWWTP Substation 1 and primary switchgear. The change covers increased PPL-related costs, directional drilling, and installation of a new manhole, bringing the electrical contract total to $5,088,960.15 without extending the schedule.

Contract Details

Contract Amount

$109,481.89

Vendor

PHILIPS BROTHERS ELECTRICAL CONTRACTORS INC

Agency

Lehigh county Housing Authority, PA

Contract Type

CONSTRUCTION

Document Date

September 22, 2025

Contract Term

Substantial completion January 20, 2026; final payment readiness March 22, 2026 (unchanged)

Renewal Date

2026-03-22

Renewal Info

Change Order EC-02 increases the electrical contract from $4,979,478.26 to $5,088,960.15; contract times remain substantial completion January 20, 2026 and final payment March 22, 2026.