Fire Suppression Construction at Main Sewer Plant Ongoing
- Disclosed value
- Original contract sum $175,000.00; total completed & stored to date $168,400.00; current payment due $70,488.00; balance to finish plus retainage $23,440.00 (as of 12/31/2025)
- From agenda
- Document date
- Jan 5, 2026
The 30-second brief
Guy M. Cooper, Inc. is performing construction for fire suppression systems at the main sewer plant, with $168,400 completed out of a $175,000 contract as of December 2025.
Guy M. Cooper Inc holds this construction contract with Town of Concord. Its other public contracts on record include work for Abington SD and Town of Cheltenham.
Term as filed: Construction; Application for Payment #4 through 12/31/2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Original contract sum $175,000.00; total completed & stored to date $168,400.00; current payment due $70,488.00; balance to finish plus retainage $23,440.00 (as of 12/31/2025)
- Document date
- January 5, 2026
- Term
- Construction; Application for Payment #4 through 12/31/2025
- Vendor
- Guy M. Cooper Inc
- Agency
- Town of Concord
- Source document
- Concord Township Council Agenda January 2026 (Agenda)
Guy M. Cooper Inc's other public contracts
More Town of Concord contracts
Questions about this contract
Who was awarded the construction contract by Town of Concord?
Guy M. Cooper Inc was awarded this construction contract by Town of Concord, as recorded on January 5, 2026. The contract value is Original contract sum $175,000.00; total completed & stored to date $168,400.00; current payment due $70,488.00; balance to finish plus retainage $23,440.00 (as of 12/31/2025).
How much is the Guy M. Cooper Inc contract with Town of Concord worth?
The Guy M. Cooper Inc contract with Town of Concord is valued at Original contract sum $175,000.00; total completed & stored to date $168,400.00; current payment due $70,488.00; balance to finish plus retainage $23,440.00 (as of 12/31/2025), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Concord Township Council Agenda January 2026 (Agenda), dated January 5, 2026 from Town of Concord. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Guy M. Cooper Inc hold?
Guy M. Cooper Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Concord currently buying?
Explore Town of Concord's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.