CONSTRUCTIONAMENDED

Operations Center GMP Amendment Approved for Hood Construction

Fort Mill Town Council approved an amendment to its Construction Manager contract with Hood Construction, setting a Guaranteed Maximum Price of $38,858,984 for the Operations Center project. The amendment also adjusts the completion timeline to 15 months and includes designated contingency and allowance funds.

Status
AMENDED
Document date
May 18, 2026
Contract type
CONSTRUCTION
Vendor
Hood Construction
Agency
Town of Fort Mill · SC

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$38,858,984 (includes $1,250,000 contingency and $379,000 in allowances; total project cost approximately $38.25 million)
Contract type
CONSTRUCTION
Contract term
15 months completion timeline for Operations Center
Renewal
Amendment to existing Construction Manager contract sets a Guaranteed Maximum Price and revises the completion schedule to 15 months; no explicit renewal options noted.
Document type
Minutes
Source document
Fort Mill Town Council Minutes 2026-05-18

Related contracts

Other contracts from Hood Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Fort Mill?

Hood Construction was awarded this construction contract by Town of Fort Mill, as recorded on May 18, 2026. The contract value is $38,858,984 (includes $1,250,000 contingency and $379,000 in allowances; total project cost approximately $38.25 million).

How much is the Hood Construction contract with Town of Fort Mill worth?

The Hood Construction contract with Town of Fort Mill is valued at $38,858,984 (includes $1,250,000 contingency and $379,000 in allowances; total project cost approximately $38.25 million), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Fort Mill Town Council Minutes 2026-05-18 (Minutes), dated May 18, 2026 from Town of Fort Mill. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Hood Construction hold?

Hood Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Hood Construction's profile

What is Town of Fort Mill currently buying?

Explore Town of Fort Mill's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Fort Mill's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free