WWTF Phase 2A contract amended for panel relocation
Trusted by teams at
Description
The City of Salem approved Change Order No. 3 with Midstate Pipeline Maintenance LLC for the WWTF Phase 2A project, adding $9,428 in work to relocate and elevate the leachate pump station control panel. The amendment raises the total contract to $4,298,031 and extends completion to June 19, 2026.
Contract Details
Contract Amount
Increase of $9,428.00; new total contract amount $4,298,031.00
Vendor
MIDSTATE PIPELINE MAINTENANCE LLC
Agency
Town of Salem, MO
Contract Type
CONSTRUCTION
Document Date
April 14, 2026
Contract Term
Contract time extended 112 days to revised completion date of June 19, 2026
Renewal Date
2026-06-19
Renewal Info
Third change order to the WWTF Phase 2A contract; extends contract time by 112 days and increases total contract amount to $4,298,031.00.
More from MIDSTATE PIPELINE MAINTENANCE LLC
More from Town of Salem
City of Salem Board of Aldermen Agenda 2026-05-26
City of Salem Board of Aldermen Agenda 2026-05-26
City of Salem Board of Aldermen Agenda 2026-05-26
City of Salem Board of Aldermen Agenda Packet 2026-05-26
City of Salem Board of Aldermen Agenda Packet 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.