City of Salem Board of Aldermen Meeting Agenda Packet April 2026

WWTF Phase 2A contract amended for panel relocation

Increase of $9,428.00; new total contract amount $4,298,031.00Town of SalemMIDSTATE PIPELINE MAINTENANCE LLCApril 14, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Salem approved Change Order No. 3 with Midstate Pipeline Maintenance LLC for the WWTF Phase 2A project, adding $9,428 in work to relocate and elevate the leachate pump station control panel. The amendment raises the total contract to $4,298,031 and extends completion to June 19, 2026.

Contract Details

Contract Amount

Increase of $9,428.00; new total contract amount $4,298,031.00

Vendor

MIDSTATE PIPELINE MAINTENANCE LLC

Agency

Town of Salem, MO

Contract Type

CONSTRUCTION

Document Date

April 14, 2026

Contract Term

Contract time extended 112 days to revised completion date of June 19, 2026

Renewal Date

2026-06-19

Renewal Info

Third change order to the WWTF Phase 2A contract; extends contract time by 112 days and increases total contract amount to $4,298,031.00.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free