Tarrant Regional Water District AgendaPacket 2026-06-16

Retainage Reduced for Gadberry Construction Electrical Room Project

$415,259.96 (retainage, 5% of contract price), total contract price $8,305,199.13TARRANT REGIONAL WATER DISTRICT A WCIDGADBERRY CONSTRUCTIONJune 16, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Tarrant Regional Water District approved a reduction in retainage to 5% ($415,259.96) of the contract price with Gadberry Construction for electrical room cooling improvements at the Richland-Chambers High-Capacity Pump Station. The board found satisfactory progress at the 50% completion point and received surety consent.

Contract Details

Contract Amount

$415,259.96 (retainage, 5% of contract price), total contract price $8,305,199.13

Vendor

GADBERRY CONSTRUCTION

Agency

TARRANT REGIONAL WATER DISTRICT A WCID, TX

Contract Type

CONSTRUCTION

Document Date

June 16, 2026

Renewal Info

Retainage percent adjusted on reaching 50% completion. Further retainage updates per change orders as needed.

More from GADBERRY CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free