Marin Community College District Regular Board Meeting Agenda 2026-05-19

Change Order Raises Tricon PE Renovation Contract to $3.89M

$240,000 change order (from $3,649,517 to $3,889,517 total)Kentfield ElementaryTRICON CONSTRUCTION INCMay 19, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Marin Community College District will consider approving Change Order 02 with Tricon Construction, Inc. for the Kentfield Campus PE Complex Renovations, increasing the contract by $240,000 to a new total of $3,889,517. The adjustment covers added work arising from weather-related impacts and unforeseen conditions, funded from project contingency.

Contract Details

Contract Amount

$240,000 change order (from $3,649,517 to $3,889,517 total)

Vendor

TRICON CONSTRUCTION INC

Agency

Kentfield Elementary, CA

Contract Type

CONSTRUCTION

Document Date

May 19, 2026

Renewal Info

Second change order to the existing PE Complex Renovations construction agreement, increasing the owner's allowance and new total contract value to $3,889,517.