B5 Water Plant No. 2 contract reduced to $1.95M

Reid Road MUD No. 1 approved Change Order No. 5 with B5 Construction for the completed Water Plant No. 2 recovery project, reducing the final contract amount to $1,949,985 and authorizing payment of the final pay estimate. The district will seek insurance reimbursement for related costs.

Document date · March 18, 2026

Track Reid Road Mud 1 contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Reid Road Mud 1.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Final contract amount $1,949,985
Contract type
CONSTRUCTION
Renewal
Change Order No. 5 decreased the overall contract sum for the Water Plant No. 2 recovery project to $1,949,985 and marked final payment.
Document type
Minutes
Source document
Reid Road Municipal Utility District No. 1 Board of Directors Meeting Minutes March 2026

Related contracts

Other contracts from B5 Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Reid Road Mud 1?

B5 Construction was awarded this construction contract by Reid Road Mud 1, as recorded on March 18, 2026. The contract value is Final contract amount $1,949,985.

How much is the B5 Construction contract with Reid Road Mud 1 worth?

The B5 Construction contract with Reid Road Mud 1 is valued at Final contract amount $1,949,985, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Reid Road Municipal Utility District No. 1 Board of Directors Meeting Minutes March 2026 (Minutes), dated March 18, 2026 from Reid Road Mud 1. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does B5 Construction hold?

B5 Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.