CONSTRUCTIONAWARDED

Town of Danville Awards Construction Contract to Insituform Technologies Llc (September 2026)

The Town of Danville Town Council approved Resolution No. 75-2026 awarding a $1,226,003 construction contract, with a total budget of $1,410,003 including contingency, to Insituform Technologies, LLC for trenchless rehabilitation of storm drain pipes along San Ramon Valley Boulevard and Hill Meadow Place under CIP A-330. Work is planned to start in late 2026 and finish in early 2027.

Document date · September 1, 2026

Track Town of Danville contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Town of Danville.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$1,226,003 plus 15% contingency not-to-exceed $184,000 (total construction budget $1,410,003)
Contract type
CONSTRUCTION
Contract term
Work scheduled to begin in late 2026 and be completed in early 2027
Renewal date
2027-03-31
Renewal
One-time construction contract for CIP No. A-330 storm drain rehabilitation, with a 15% contingency allowance; no renewals or extensions described.
Document type
StaffReport
Source document
Town of Danville Staff Report Resolution No. 75-2026 Awarding a Construction Contract for the San Ramon Valley Boulevard & Hill Meadow Place Storm Drain Rehabilitation Project 2026-09-01

Related contracts

Other contracts from Insituform Technologies Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Danville?

Insituform Technologies Llc was awarded this construction contract by Town of Danville, as recorded on September 1, 2026. The contract value is $1,226,003 plus 15% contingency not-to-exceed $184,000 (total construction budget $1,410,003).

How much is the Insituform Technologies Llc contract with Town of Danville worth?

The Insituform Technologies Llc contract with Town of Danville is valued at $1,226,003 plus 15% contingency not-to-exceed $184,000 (total construction budget $1,410,003), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Town of Danville Staff Report Resolution No. 75-2026 Awarding a Construction Contract for the San Ramon Valley Boulevard & Hill Meadow Place Storm Drain Rehabilitation Project 2026-09-01 (StaffReport), dated September 1, 2026 from Town of Danville. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Insituform Technologies Llc hold?

Insituform Technologies Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Insituform Technologies Llc's profile

What is Town of Danville currently buying?

Explore Town of Danville's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Danville's profile