CONSTRUCTIONONGOING

J.L. Cobb Contract for SCC Retrofit Updated

Rancho Santiago Community College District tracked the Building B-203 Retrofit Project at Santiago Canyon College under contract with J.L. Cobb, Inc. The original contract was $107,838 and one change order added $488, bringing the revised total to $108,326.

Document date · September 14, 2026

Track Santa Ana College contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Santa Ana College.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Original Contract Amount $107,838.00; Total Change Orders $488.00; Revised Contract Amount $108,326.00
Contract type
CONSTRUCTION
Contract term
Notice to Proceed 6/17/2026; Original Contract Duration 60 days; Original Completion Date 8/16/2026; Final Completion Date 8/16/2026
Renewal date
2026-08-16
Renewal
Original contract began with notice to proceed on 6/17/2026 and had a 60-day duration. The revised completion date remained 8/16/2026; one change order was recorded.
Document type
Contract
Source document
Rancho Santiago Community College District Contract Summary Building B-203 Retrofit Project at Santiago Canyon College 2026-09-14

Related contracts

Other contracts from J.l. Cobb Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Santa Ana College?

J.l. Cobb Inc was awarded this construction contract by Santa Ana College, as recorded on September 14, 2026. The contract value is Original Contract Amount $107,838.00; Total Change Orders $488.00; Revised Contract Amount $108,326.00.

How much is the J.l. Cobb Inc contract with Santa Ana College worth?

The J.l. Cobb Inc contract with Santa Ana College is valued at Original Contract Amount $107,838.00; Total Change Orders $488.00; Revised Contract Amount $108,326.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Rancho Santiago Community College District Contract Summary Building B-203 Retrofit Project at Santiago Canyon College 2026-09-14 (Contract), dated September 14, 2026 from Santa Ana College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does J.l. Cobb Inc hold?

J.l. Cobb Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View J.l. Cobb Inc's profile

What is Santa Ana College currently buying?

Explore Santa Ana College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Santa Ana College's profile