CONTRACTPENDING

CDBG Funds Sidewalk Improvement Construction Projects

San Diego County logoSan Diego County
Disclosed value
$600,000 (construction contract estimate, including 25% contingency); $180,000 additional CDBG appropriations; total project cost $810,000
From minutes
Document date
May 22, 2024

The 30-second brief

What it covers

The Board of Supervisors approved additional $180,000 in Community Development Block Grant-funded appropriations and authorized advertisement and award of an estimated $600,000 construction contract for pedestrian facility improvements in Fallbrook and Ramona. Construction is slated to start in Fall 2024 and conclude in Winter 2024, enhancing ADA-compliant sidewalks and ramps in low- and moderate-income areas.

Who holds it

Community Development Block Grant holds this construction contract with San Diego County. Its other public contracts on record include work for City of Bangor and City of New Smyrna Beach.

What happens next

Term as filed: Construction scheduled to begin Fall 2024 and be completed Winter 2024.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$600,000 (construction contract estimate, including 25% contingency); $180,000 additional CDBG appropriations; total project cost $810,000
Document date
May 22, 2024
Term
Construction scheduled to begin Fall 2024 and be completed Winter 2024
Source document
County of San Diego Board of Supervisors Minutes 2024-05-22 (Minutes)

Community Development Block Grant's other public contracts

More San Diego County contracts

Questions about this contract

Who was awarded the construction contract by San Diego County?

Community Development Block Grant was awarded this construction contract by San Diego County, as recorded on May 22, 2024. The contract value is $600,000 (construction contract estimate, including 25% contingency); $180,000 additional CDBG appropriations; total project cost $810,000.

How much is the Community Development Block Grant contract with San Diego County worth?

The Community Development Block Grant contract with San Diego County is valued at $600,000 (construction contract estimate, including 25% contingency); $180,000 additional CDBG appropriations; total project cost $810,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in County of San Diego Board of Supervisors Minutes 2024-05-22 (Minutes), dated May 22, 2024 from San Diego County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Community Development Block Grant hold?

Community Development Block Grant may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is San Diego County currently buying?

Explore San Diego County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →