CONSTRUCTIONONGOING

District Nears Completion of Ice Tank Replacement Contract

The School District of Lee County engaged Trane Technologies Company, LLC under a GSA piggyback contract 47QSWA20D002A for the River Hall Elementary School Ice Tank Replacements Project, with a final contract amount of $864,600.84. The Internal Compliance Department recommends releasing the remaining $43,230.04 retainage as final payment following completion, final inspection, and required approvals.

Document date · July 9, 2025

Track Lee County School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Lee County School District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$864,600.84 (final contract amount); final payment/retainage $43,230.04
Contract type
CONSTRUCTION
Contract term
Contract dated May 14, 2024; work began September 2024; Consent of Surety to Final Payment dated March 20, 2025
Renewal date
2025-03-20
Renewal
No change orders were issued, and this appears to be a one-time construction project with retainage released upon final completion; no renewal provisions are mentioned.
Document type
Report
Source document
The School District of Lee County Report River Hall Elementary School Ice Tank Replacements Project 2025-07-09

Related contracts

Other contracts from Trane Technologies Company Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Lee County School District?

Trane Technologies Company Llc was awarded this construction contract by Lee County School District, as recorded on July 9, 2025. The contract value is $864,600.84 (final contract amount); final payment/retainage $43,230.04.

How much is the Trane Technologies Company Llc contract with Lee County School District worth?

The Trane Technologies Company Llc contract with Lee County School District is valued at $864,600.84 (final contract amount); final payment/retainage $43,230.04, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in The School District of Lee County Report River Hall Elementary School Ice Tank Replacements Project 2025-07-09 (Report), dated July 9, 2025 from Lee County School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Trane Technologies Company Llc hold?

Trane Technologies Company Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Trane Technologies Company Llc's profile

What is Lee County School District currently buying?

Explore Lee County School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Lee County School District's profile