CONSTRUCTIONAMENDED

Flint Design Build Gets STEAM Project Change Order

Chabot-Las Positas Community College District approved Change Order #009 for Flint Design Build LLC on the Las Positas College STEAM project. The change order adds $84,919 to the contract, bringing the total to $114,167,131, while the construction-phase duration remains 645 days.

Document date · June 24, 2026

Track Las Positas College contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Las Positas College.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
The CONTRACT Sum will be increased by this Change Order $84,919.00; the new CONTRACT Sum (Including this Change Order) is $114,167,131.00
Contract type
CONSTRUCTION
Contract term
Contract Time for the Construction Phase: 645 days; Date of Project Completion as of the date of this Change Order: November 2, 2028
Renewal date
2028-11-02
Renewal
Change Order #009 amends Contract #B240260; contract time is unchanged. The document references prior authorized change orders and updates the contract sum and contingency balances.
Document type
Contract
Source document
Chabot-Las Positas Community College District Contract Change Order STEAM Project at Las Positas College 2026-06-24

Related contracts

Other contracts from Flint Design Build Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Las Positas College?

Flint Design Build Llc was awarded this construction contract by Las Positas College, as recorded on June 24, 2026. The contract value is The CONTRACT Sum will be increased by this Change Order $84,919.00; the new CONTRACT Sum (Including this Change Order) is $114,167,131.00.

How much is the Flint Design Build Llc contract with Las Positas College worth?

The Flint Design Build Llc contract with Las Positas College is valued at The CONTRACT Sum will be increased by this Change Order $84,919.00; the new CONTRACT Sum (Including this Change Order) is $114,167,131.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Chabot-Las Positas Community College District Contract Change Order STEAM Project at Las Positas College 2026-06-24 (Contract), dated June 24, 2026 from Las Positas College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Flint Design Build Llc hold?

Flint Design Build Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Flint Design Build Llc's profile

What is Las Positas College currently buying?

Explore Las Positas College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Las Positas College's profile